Aspen/Pitkin County Airport (ASE) has set its dates for a long closure in 2027. The airport will shut at 11 p.m. on Sunday, April 4, 2027, and reopen at 7 p.m. on Friday, November 19, 2027, so crews can rebuild the runway. No airline or private flights will be allowed during that time.

What is being built

According to the airport's announcement and reporting by The Aspen Times, voters approved the project. The runway will be completely rebuilt to meet current FAA standards. Work on a new airline terminal and a new fixed-base operator (FBO) building will also start in April 2027. The airport's fact sheet gives more detail:

  • The runway will be widened from 100 to 150 feet and moved about 80 feet west.
  • The current wingspan limit of 95 feet is expected to rise to 118 feet after the rebuild.
  • Airlines will keep using the existing terminal after the runway reopens, until the new terminal opens in 2029.

Early work began in summer 2026. It includes moving Owl Creek Road and the bike path next to it, plus some utility work. The airport says the schedule depends on the weather and could change.

What it means for travelers

The closure starts in early April, so the end of the 2026–27 ski season is not affected. It does cover the entire summer and early fall of 2027. For private flights, the airport names Rifle Garfield County Airport as the general aviation alternative. For airline service, it lists Vail/Eagle County, Grand Junction, Montrose and Denver. The airport will also be closed to helicopters, which it directs to Glenwood Springs or Rifle.

Summer 2027 trips to Aspen will mean a longer drive from the airport, so allow extra time. Book aircraft and ground transportation early, because other travelers will be using the same alternate airports. For current fees and flight times, see our Aspen airport guide and the Los Angeles to Aspen route.